DUQM Liquid Bulk Berths Project

Sultanate of Oman

Introduction
The Government of The Sultanate of Oman is in the process of developing Duqm town and the Port of Duqm, as a strategic dry dock, free trade zone, industrial and tourism destination. The Port of Duqm is seen as a catalyst for the development of the Al Wusta region. The Port and Dry Dock are being developed to increase the trade; i.e. cargo trans-shipments, ship repair, manufacturing and tourism. The site enjoys proximity to the busy regional sea-lanes of Oman’s coastal waters and is characterized by a friendly climate.
dqewr.png
Location map and mater plan details.
ESC Scope of Supply
ESC was awarded the job to supply 5,046MT of painted LSAW pipe (specification: OD1219, thickness 22mm, length from 13m ~ 24.5m) with material API Spec. 5L grade X60. The LSAW pipe is required to be fabricated in accordance with client supplied project specific specifications. 
Corrosion Protection System
Interzone 505 (Total DFT: 800µm), Surface cleanliness: Sa2.5
Picture2.png

Project Photos

PRE-BLASTING INSPECTION

Visual inspection to ensure no grease and surface quality achieve

press to zoom

Ambient condition checking

press to zoom

Abrasive contamination checking

press to zoom

Abrasive contamination checking

press to zoom

Shot blasting to ISO 8503 Sa 2.5

press to zoom
shot blasting
shot blasting

Shot blasting to ISO 8503 Sa 2.5

press to zoom

POST-BLASTING INSPECTION

Compressed air cleanliness inspection as accordance with ASTM D4285

press to zoom

Dust purging using compressed air

press to zoom

Dust test comply with ISO 8502-3 minimum Class 2

press to zoom

Dust test comply with ISO 8502-3 minimum Class 2

press to zoom

Check surface cleanliness to ensure comply with ISO 8503 Sa 2.5

press to zoom

Surface roughness inspection as accordance with ASTM D4417 Method C

press to zoom

Salt contamination test as accordance with ISO 8502-9

press to zoom

Salt contamination test as accordance with ISO 8502-9

press to zoom

PAINTING PREPARATION /PAINTING

Temperature control paint Storage room

press to zoom

Verification of painting material

press to zoom

Paint Mixing

press to zoom

Paint Mixing

press to zoom

Stripe coat

press to zoom

Check amount of thinner added

press to zoom

Paint temperature checking

press to zoom

Substrate temperature check

press to zoom

Monitor paint mixing ratio

press to zoom

Automatic painting

press to zoom

WFT Inspection

press to zoom

CURING

Curing room with temperature & humidity control

press to zoom

Curing room with temperature & humidity control

press to zoom

Elcometer in curing room

press to zoom

Elcometer in curing room

press to zoom

Dehumidifier in curing room

press to zoom

Heater

press to zoom

Curing Room Inspection:

  • Ensure humidity <80%, temperature >10°C

  • Ensure pipe stand position located at top <170mm and bottom <400mm

FINAL INSPECTION

DFT inspection as accordance with SSPC PA2

press to zoom

DFT inspection as accordance with SSPC PA2

press to zoom

Measuring magnifier inspection

press to zoom

Adhesion test as accordance with ASTM D3359

press to zoom

Pipe painting status marking

press to zoom

DFT Inspection Report

press to zoom

Climate Inspection Report

press to zoom
press to zoom
pa 21
pa 21
press to zoom